THE Metropolitan Manila Development Authority (MMDA) has proposed the construction of rainwater impounding facilities inside Camp Aguinaldo to ease recurring flooding on EDSA, with the proposed design released on Wednesday, Aug. 27.
The plan requires detention ponds that will temporarily store excess rainwater during downpours and gradually release it into the EDSA drainage system, leading to the Makiling Creek.
As proposed, the project will be implemented in three phases, covering 182 hectares and involving a golf course near Gate 2, another near Gates 3 and 4, and an open space near Gate 6.
MMDA proposes rainwater facilities in Camp Aguinaldo to mitigate EDSA flooding
For the first phase near Gate 2, the detention pond has a 361-meter perimeter, a 4,650-square-meter area, an 8-meter depth, and a 37,200-cubic-meter capacity, designed for a 25-year return period (15.6 mm per hour over 24 hours), exceeding the needed 36,945 cubic meters.
MMDA’s schematic shows that under normal weather, the water bypasses the pond and flows through the lagoon to EDSA.
During heavy rain, floodgates divert water flow into the pond; after rain, pumps discharge stored water slowly into EDSA toward the Makiling Creek.
The scope of works covers the impounding area, operations and powerhouse, drainage and electromechanical works, and landscaping and golf course restoration, with a treatment facility under consideration., This news data comes from:http://xym-mn-up-dei.gyglfs.com

Officials said operations and maintenance arrangements, and a memorandum of agreement, are still under discussion.
- Recto: No exemption for US tech firms from digital tax
- Pagasa monitors 2 LPAs inside PAR; prevailing 'habagat' brings rain across PH
- Makati earns high rating in anti-trafficking and violence assessment
- Govt debt swells to record P17.58T
- US church shooter 'obsessed with idea of killing children'
- NKorea could produce ten to twenty nukes per year — SKorea leader
- Putin meets Kim, praises North Korean troops in Russia
- No winner in lotto draws for Aug 30
- Repairs on Chinese ship in Bajo de Masinloc collision may take 2 months - PH Navy
- Marcos names acting Ombudsman